Circle Redmont
 
Company Services Products Applications Gallery Newsroom Contact Architect / Builder Resources
 
1-800-358-3888
True Green
Testimonials
Click here to opt in!
 
cr archive for January 2010

Stanford Deck Skylights Get Extreme Makeover

Monday, January 25th, 2010

Stanford Deck Skylights Get Extreme Makeover

By: Heidi Y. Granke, AIA

Original Project Conditions and Goals
The original problem, which this project corrected, was water infiltration into the below-ground restroom building. The existing conditions included a porous concrete deck and porous brick masonry walls. The existing roof structure is a concrete deck, which had an approximately 1 ½” shallow concrete topping. Water was absorbing into the concrete and seeping into the restroom below. The task of waterproofing the building was achieved by injecting the walls with Hydro Active Injecto Grout by de neef Construction Chemicals Inc. and by adding an Elasto Deck 5500 waterproofing
membrane onto the deck.

Stanford original deck installation

Stanford original deck installation

Other constraints on the project included: requirements to match the grade level along the arcade, existing stairs and curbs at grills in adjacent buildings, no water could drain over the arcade and the finished appearance needed to match as closely as possible the existing appearance. The grade at the arcade is only about 1” above the structural slab over the bathroom.


Original Topping Installation

There were several issues related to the topping installation. First, the polymer topping is more difficult to work than typical concrete topping. The polymers, aggregate, and fibers in the mix make it stiffer. Second, the polymers in the mix and the shallow depth make the topping set up more quickly than standard concrete. Third, the topping was installed by a roofing installer not familiar with working with polymers. The result was an uneven slab that had low spots with minor ponding. Another issue was the perceived wetness of the topping. A sealer was applied over the topping to prevent dirt infiltration, which also increased the water repellency of the topping and made the topping look shiny. The wet appearance of the slab was perceived as slippery. However, the aggregate in the topping and the sandblasted finish provide a surface with good traction, even when wet.


Skylights

The project team decided to try to repair the skylights to insure that the entire deck system was watertight. After looking into several different methods and possible suppliers, it was decided to send the skylights to Circle Redmont for revaluation and repair or replacement. Circle Redmont determined that the cast-iron pans were severally corroded under the concrete topping and therefore recommended replacement over repair. HDCCO sent a sample of the concrete topping to Circle Redmont for them to match the color. D. M. Figley sent the topping materials for Circle Redmont to test and consider for use in the skylights. They had difficulty with the polymer topping mix cracking when it was sand blasted. Therefore, they decided to use their own proprietary mix instead of the Exel-crete. Multiple samples were sent to the project team for review until the sample was approved. The final sample was approved on October 29, 2009. The skylights were reviewed on site on December 15. They were installed on December 23, 2009. 


Topping Repairs
In 2009, as the project repairs and the skylight installation are being planned, the project team once again reviewed the topping materials. At the July 14, 2009 meeting, Sapna expressed concerns about the polymer slab because of the testing that was conducted by the skylight manufacturer., Circle Redmont. Circle Redmont found the polymer concrete unsuitable for installation in the skylights because the material cracked when sandblasted. Therefore, the types of materials and possible combinations were again reviewed; including a few options not previously review.

The final decision was to re-top to the slab with the same material, but to apply it in small controlled areas so that it could be worked more easily. 

Stanford new deck

Stanford new deck


Final Testing

Hathaway Dinwiddie tested the deck and skylights for water tightness and drainage on December 29, 2009. At 9 am the deck was flooded with water and was monitored every hour throughout the day to insure that there were no leaks. The weather was 51 degrees Fahrenheit at the beginning of the day and the high for the day as 56 degrees. The day was mostly overcast, so little or no direct sunlight fell on the deck. The deck and skylights performed well: there were no leaks and the deck drained
properly. Attached are the hour by hour photographs of the testing. 

Stanford new deck watertest

Stanford new deck watertest


Conclusion

The project accomplished the primary goal of making the restroom water tight.

Stanford bathroom underneath

Stanford bathroom underneath

Posted in news releases | Comments Off

Circle Redmont Builds the Ultimate Playhouse

Friday, January 8th, 2010

NEWS RELEASE
November 24, 2009
Media Contact: Mike McBride
McBride Woodbridge Marketing 321.837.1000
 

CIRCLE REDMONT BUILDS THE ULTIMATE PLAYHOUSE
For Habitat for Humanity “LIGHTFEST” Raffle

[MELBOURNE, FL] – Circle Redmont, in partnership with Prime Bank of Melbourne, custom built and donated a Key West style playhouse as part of the “Space Coast Lightfest” display in Wickham Park. The house is one of six playhouses to be raffled on December 23. Proceeds from the raffle benefit Habitat for Humanity of Brevard County, Inc.


Circle Redmont workers pose with completed playhouse

Unique custom features of the children’s playhouse include hurricane rated glass block windows, stand seam metal roofing, interior tile flooring and a wrap-around porch. The exterior is adorned with custom-fabricated pineapple lamps, shutters, tropical signs and fascia scrolling with glass circle insets. Inside, the house comes complete with interior lighting and an Internet/cable hookup.


Elegant details work throughout the playhouse

The house not only features the Key West style requested by Prime Bank, it is also a hurricane resistant structure. Dana Kilborne, president of Prime Bank, called the experience of working with Circle Redmont nothing short of fantastic.

“We initially contacted Circle Redmont to request the use of their facility so we could build the house ourselves. When Fred [Sandor] and Jeff [Barrett] learned about the project, they insisted on being a part of it.”


Partner Jeff Barrett applies the “Jeff touch”

Circle Redmont specializes in structural glass, being both expert artisans and manufacturers. Their work can be found all over the country, including the Millennium Towers in Chicago and Time Square in New York. Building a playhouse was a new venture.


House was designed to be moved on a single pallet

“The final result exceeded our expectations,” said Kilborne. “We have the best partner in Circle Redmont and trust that our Key West playhouse will assist Habitat for Humanity in continuing its good work throughout the county.”

“All of us at Circle Redmont were thrilled to be involved with this project and extremely proud of the outcome,” said Fred Sandor of Circle Redmont. “I’ve heard a few of our employees say they wouldn’t mind living in the playhouse. It’s very cozy and durable.”


Custom-crafted pineapple light and festive porch furniture

Each car admission to the “Lightfest” display comes with a raffle ticket, and additional tickets can be purchased for $5 at Fidelity Bank of Florida in Merritt Island, Prime Bank on Wickham and the Habitat for Humanity office in West Melbourne. Admission to the display is $10 per carload.


Senior Partner Fred Sandor leaves holiday message

For more information on the holiday playhouse raffle visit www.brevardhabitat.com. For more information on Circle Redmont, visit their website at www.circleredmont.com.

Posted in news releases | Comments Off

Categories

3d renderings & prototypes
builder misconceptions
glass standards
installation factors
news releases
plank glass facts
project profiles
the cr specification



  • Archives


  •  
    home company products services applications markets newsroom testimonials contact requests
     
    All photos and designs found on this web site are the sole property of Circle Redmont. Any reproduction or unauthorized use of the photos and/or content on this web site will be subject to prosecution as stated in the laws governed by the state of Florida. Site Designed and Developed by McBride Marketing Group.

    Copyright © Circle Redmont 2011. All Rights Reserved

    sitemap
    Circle Redmont Read what architects & builders say